Jeddah Tower is the reinforced-concrete megatall rising on the Red Sea coast of Saudi Arabia, designed by Adrian Smith + Gordon Gill Architecture to become the first building in history to pass one kilometer. Its recent biography runs: halted for seven years at 63 floors, restarted under a SAR 7.2 billion completion contract in late 2024, and climbing since at a pace its owner describes as a five-day floor cycle. In the developer’s own Saudi Exchange filings, the project is the Jeddah Economic Company Tower, and the trade press has begun calling it the JEC Tower – the name “Jeddah Tower” survives as the world’s shorthand.
Project Data
Official name: Jeddah Economic Company Tower (JEC Tower); widely known as Jeddah Tower, formerly Kingdom Tower
Status: under construction; structure past the 100th floor and rising
Final height: at least 1,000 meters (3,281 ft); exact figure undisclosed until completion
Floors: at least 157 · Observation deck: 630 meters, planned world’s highest
Area: 530,000 m² total built area; 243,866 m² tower gross floor area · Parking: 2,205 spaces
Design: Adrian Smith + Gordon Gill Architecture · Structure: Thornton Tomasetti · Wind Engineering: RWDI · Civil/Geotechnical Engineering: Langan · Engineering support: Dar Al-Handasah · Project Management: Turner International
Contractor: Saudi Binladin Group · Elevators: KONE · Glazing: Guardian Glass
Client: Jeddah Economic Company; principal investor Kingdom Holding Company, chaired by Prince Alwaleed bin Talal
Completion Target: late 2028
Location: Jeddah Economic City, north Jeddah, Saudi Arabia
Construction Status
Jeddah Tower’s construction status, as last announced, is Level 118 and approximately 474 meters, reached in early October 2026. Ian Norman Miller, senior executive project director at Saudi Binladin Group, announced it in a social-media post on LinkedIn celebrating the latest concrete pour, and Arabian Business reported it on October 6, 2026, noting that the height puts the unfinished tower level with New York’s Central Park Tower (472.4 meters) and the Wuhan Greenland Center (475.6 meters), per the Council on Tall Buildings and Urban Habitat. It is the latest announced figure as of October 2026. The previous marker came from the developer: Fabien Toscano, chief executive of Jeddah Economic Company, told MEED’s Shaping Mega Projects conference in Riyadh on September 29, 2026 that the tower had reached its 116th floor, at about 466 meters, leaving 41 of its 157 planned floors to build. Before that, Miller had announced 454 meters and 113 floors on September 2, 2026, passing Malaysia’s 452-meter Petronas Towers, as Newsweek reported.
Kingdom Holding’s second-quarter 2026 results, released on August 7, 2026 and reported by Reuters via Zawya, describe the site at that earlier stage:
- the tower at level 106 and 430 meters
- more than 300,000 cubic meters of concrete poured, about 67 percent of the total
- more than 3,000 façade panels installed, about 11 percent of the cladding
- nearly 6,400 workers on site
- more than 16 million work-hours without a lost-time incident, and zero fatalities
The same results reported first-half revenue down 12 percent year on year, to SAR 1.2 billion, and net profit down about 28 percent, to SAR 602 million, in the figures filed with the Saudi Exchange. Jeddah Economic Company is carried at its year-end 2025 valuation until a revaluation at the end of 2026. On August 5, 2026, The Media Line put the remaining climb at about 570 meters from the 430-meter mark, attributing the count to Kingdom Holding. The owner’s 2025 financial statement, released in March 2026, had described mechanical, electrical, and plumbing works in progress alongside the superstructure and an average five-day floor cycle. Glass cladding is visible on the tower’s lower reaches in the construction photographs AS+GG released in April 2026.
John Peronto of Thornton Tomasetti estimated in June 2026 that the structure could reach 500 meters in about 25 weeks and the upper observation zone roughly 60 weeks out – dated projections at the pace of the time rather than commitments. The tower’s height fraction is also not its completion fraction, because façade, services, interiors, and commissioning run on their own schedules. The August filing shows the gap in its own numbers: two thirds of the concrete against a tenth of the façade cladding. Concrete remains the better single statistic. Thornton Tomasetti put it at more than half of the total in January 2026, and Kingdom Holding at about 67 percent in August.
Timeline: 2013 Groundbreaking to the 2024 Restart Contract
The tower’s timeline divides cleanly on October 2, 2024. Construction had begun on April 1, 2013, reached 63 floors, and stopped in January 2018 amid contractor payment disruptions and the upheaval surrounding the project’s principal backer (see “The 2018 Halt” below). For seven years, the unfinished core stood as Jeddah’s most conspicuous question mark. Then Jeddah Economic Company signed a completion agreement with Saudi Binladin Group, disclosed through the Saudi Exchange: SAR 7.2 billion (about US$1.9 billion), including roughly SAR 1.1 billion attributed to prior works, on a 42-month execution program financed through internal funds and banking facilities. Work resumed in January 2025 from the 63rd floor.
Kingdom Holding marked the restart with a ceremony on January 20, 2025; Dezeen reported that concrete was poured on the 64th floor. The company’s official X account – a social post rather than a publication – lists those present:
- Prince Alwaleed bin Talal, Kingdom Holding’s chairman
- Talal Al Maiman, its CEO
- Sheikh Yaslam bin Laden of the Bin Laden Group
- Hassan Sharbatly of Qilla Jeddah for Real Estate Investments
- Mohammed Al-Qatari of Abraar International Company Limited
“Today’s ceremony represents the realization of a vision that took years in the making,” Al Maiman said, according to the post. He also said: “Jeddah Tower will serve as a beacon of innovation and a catalyst for growth.” Dezeen reported Kingdom Holding’s statement: “Construction of the Jeddah Tower, a global symbol of ambition and progress, has officially restarted.” According to Dezeen, a representative of the developer said they expected to complete a floor every four days. The owner’s March 2026 statement reported an average five-day cycle.
The ascent since then is a documented chain, every link attributed:
| Date | Milestone | Source |
|---|---|---|
| Oct 2, 2024 | Completion agreement signed; 63 floors completed | Saudi Exchange disclosure |
| Jan 20, 2025 | Construction and concrete pouring officially resume; concrete poured on the 64th floor | Kingdom Holding Company; Dezeen |
| Nov 28, 2025 | Central core reaches floor 69 | New Atlas, citing AS+GG |
| Jan 6, 2026 | Tower nearing 80 floors | Thornton Tomasetti |
| Mar 25, 2026 | Level 91, approximately 370 m; façade cladding and MEP works underway | Kingdom Holding Company |
| Apr 20, 2026 | 100 floors, approximately 400 m | Thornton Tomasetti |
| Jun 4, 2026 | 102 floors reported | New Atlas |
| Jul 2026 | Reported at 107 floors and 430 m | Prince Alwaleed bin Talal site-visit reporting |
| Aug 7, 2026 | Level 106 (one below the July site-visit count), 430 m; about 67% of concrete poured; about 11% of façade cladding complete | Kingdom Holding Company Q2 2026 results, via Reuters/Zawya |
| Sep 2, 2026 | 454 m (around 1,489 ft) and 113 floors, passing the 452 m Petronas Towers | Ian Norman Miller, Saudi Binladin Group, via Newsweek and Fast Company Middle East |
| Sep 29, 2026 | 116th floor, about 466 m; 41 of 157 planned floors remaining; completion targeted for late 2028 | Fabien Toscano, Jeddah Economic Company CEO, at MEED’s Shaping Mega Projects conference (via MEED, Construction Week Saudi, Gulf News) |
| Early Oct 2026 | Level 118, approximately 474 m | Ian Norman Miller, Saudi Binladin Group, via Arabian Business |
The July and August rows give the same height but differ by one floor: 107 in the site-visit reporting and level 106 in Kingdom Holding’s filing. The filing is the primary record here.
Saudi Arabia’s other gigaprojects supply the context current coverage keeps noting – with The Line scaled back and the Mukaab’s fortunes uncertain, this is the Kingdom’s marquee project still adding floors on a published schedule.
The 2018 Halt
The halt began with events off the site. In November 2017, Saudi Arabia’s anti-corruption purge locked up hundreds of royals, tycoons and government ministers for months in Riyadh’s Ritz-Carlton hotel, as AFP later summarised it. One of them was Prince Alwaleed bin Talal, Kingdom Holding’s owner, who was detained for nearly three months before being freed in January 2018; Saudi officials said he agreed to an undisclosed financial settlement, Arabian Business reported that February. Kingdom Holding then held a 33 percent stake in Jeddah Economic Company, and Saudi Binladin Group, the main contractor, held 16.6 percent. The contractor was hit directly: its chairman, Bakr bin Laden, and his brothers Saad and Saleh were detained, and the government took management control of the group after acquiring the three brothers’ collective 36.2 percent stake, according to an official document seen by AFP.
Work stopped in 2018 with the structure at the 63rd floor. In February 2018, Arabian Business was still reporting the project as going ahead: Hisham Jomah, the project’s chief development officer, said Binladin retained enough manpower and technical capacity to build the tower, while the publication noted that the contractor had been hurt by financial difficulties as the construction sector slumped. JEC chief executive Mounib Hammoud said: “We have faced delays. In projects of this magnitude you always have delays – I hope we’ll recover the delays we’ve had. We will be open for business by 2020, hopefully.” Jomah, in the same article: “Between theory and application, what has been designed and what is actually on site – that is quite another world.”
Bakr bin Laden was not released until May 2021. “He was released and told to stay home,” a source close to the family told AFP, in a report carried by France24. His brothers had been released earlier but were barred from overseas travel and initially made to wear electronic ankle bracelets. The completion agreement with Saudi Binladin Group followed in October 2024.
Origins: From a Mile-High Plan to Kingdom Tower
The kilometer tower began as a larger plan. Wikipedia, citing the trade publication MEED, records that in May 2008 soil testing cast doubt on whether the site could support the proposed one-mile (1,600-meter) tower, and that MEED reported the project scaled back by up to 500 meters. The same account puts the earlier mile-high scheme at almost US$30 billion and says that AS+GG denies involvement in that design. It dates the firm’s selection as preliminary architect to March 2010; The Skyscraper Museum dates the competition win to 2011, the year the kilometer-height design was widely reported as going ahead. The museum also records that Adrian Smith, as a partner at SOM, had led the team that won Emaar’s 2003 competition for Burj Khalifa.
The project was presented in August 2011 as Kingdom Tower. Kingdom Holding named the rest of the field in a release of February 21, 2012, announcing the final construction licence and quoting Talal Al Maiman: “Jeddah Economic Company selected the AS+GG scheme after a lengthy competition process in which SOM, Pickard Chilton, Kohn Pedersen Fox, Pelli Clarke Pelli and Foster + Partners also participated.” Prince Alwaleed, in the same release: “This project will provide sustainable profits to shareholders.”
The same release tied the tower to its city. “We envision Kingdom Tower as a new iconic marker of Jeddah’s historic importance as the traditional gateway to the holy city of Mecca,” Al Maiman said. The release states that “the southeast leg of Kingdom Tower’s tripedal base is on a direct line with the Ka’ba in Mecca, Islam’s holiest site.”
Designboom’s August 2011 presentation of the design described the slender form as “conceptually derived from the fronds of a native flower emerging from the arid desert sand.” Adrian Smith’s own account, in the same piece: “With its slender, subtly asymmetrical massing, the tower evokes a bundle of leaves shooting up from the ground – a burst of new life that heralds more growth all around it.” At its planned height of at least 1,000 meters, the tower would be twice the height of the Empire State Building, almost double One World Trade Center, and more than three times the Eiffel Tower, in Gulf News’s comparison.
Structural Engineering and Form
The tower’s form does structural work from the first sketch: AS+GG drew the tower’s floor plan as a three-winged Y that tapers continuously to the summit – the architects describe the silhouette as a bundle of young desert fronds – and the geometry does the wind engineering’s first shift: the constantly changing cross-section prevents wind vortices from organizing into the rhythmic loading that plagues uniform towers, a behavior refined through RWDI’s wind-tunnel program. The credit line runs: Smith and Gill are the architects; the buttressed-core lineage the tower extends descends from Bill Baker’s engineering at SOM on the Burj Khalifa, and here the structural design belongs to Thornton Tomasetti.
Thornton Tomasetti’s system is unusually pure for the height: interconnected reinforced-concrete walls carrying both gravity and lateral loads, with no perimeter columns, no outriggers, and no vertical transfers – a continuous load path from the summit to a 5-meter raft on 270 bored piles, each about 1.8 meters in diameter and reaching depths up to 105 meters. ENR, reporting on the foundation in November 2015, described the piles as reinforced-concrete friction piles running from 45 meters deep at the wing tips to 105 meters under the core, the deepest chosen to reduce settlement by about 75 millimeters, and the foundation as carrying a gravity load of about 860,000 tonnes. Beneath the site, ENR described up to 2 meters of silty sand over 45 to 50 meters of porous limestone “full of imprints of shells,” lying above mudstone and gravel – rock that Alan Poeppel of Langan, the geotechnical engineer, called at least an order of magnitude softer than Manhattan bedrock. Langan’s own 2011 announcement described the ground as very weak rock and highly permeable coral rock, and said the firm designed the foundation and ran a pile and barrette testing program. The concrete rises by pump, using high-strength mixes placed at heights no building project has previously demanded: ENR gave the walls throughout each floor plate as 85 MPa concrete and the total volume as about 500,000 cubic meters.
John Peronto of Thornton Tomasetti explained the structural logic to Newsweek in June 2026: “the tri-legged structure is a very efficient way to maximize stability, minimizing the amount of points of contact.” He also said: “What really drives these structures…is the fact that you have to resist such enormous gravity loads.”
Wind Engineering Above the Boundary Layer
The tapering form is the tower’s first defense against wind. Smith explained the reasoning to Arabian Business in 2011: “We learned from Burj Khalifa that the more steps you have, the better you shed the vortices, and that helps stabilize the building against any horizontal wind divergence. Kingdom Tower will do that by having a continuous series of slopes to the top, which is more effective but more expensive.” He also described the aim of the design: “Wind can move the tower from side to side and when the movement is rapid, people inside will feel it. We design to reduce that effect.”
Bill Baker of SOM made the general case to Arabian Business in July 2026: “In a tall building, gravity is more easily dealt with than lateral forces such as wind or seismic activity. For supertall buildings, wind is certainly the dominant design concern.” He added: “What we learned on Burj Khalifa is that, by shaping the building and using the appropriate structural system, the premium you pay for wind can be greatly diminished.”
At Jeddah the wind problem goes higher than usual. “One of the things that’s unique about Jeddah Tower is that really about a third of it is above the atmospheric boundary layer,” Peronto told Newsweek in June 2026. “We don’t talk about that a lot in tall buildings because not many have really achieved these levels of height.”
The upper-level wind was studied directly. Jon Galsworthy of RWDI described three datasets in Structure magazine in June 2016:
- Balloon soundings. About 17 years of balloon-sounding wind data from Jeddah International Airport, recorded at the surface and at 350, 600, and 1,000 meters.
- Mesoscale modeling. Runs of the Weather Research & Forecast (WRF) model on nested grids of 36, 12, and 4 kilometers, with 35 vertical levels up to about 16,000 meters. The runs produced 87,000 hourly records for 2001–2010.
- Boundary-layer model. A comparison against the Deaves & Harris model of the planetary boundary layer.
The balloon data alone were not enough. As Galsworthy explained to ENR in May 2016, the balloons are launched only twice a day and rarely in storms, which is why the mesoscale model was needed.
Against the measured data, the code-based wind profiles proved “quite conservative.” That finding supported a 20 percent reduction in the wind speeds used to evaluate the structure’s serviceability, and did not change the wind profiles used for the project’s strength design. The upper-level data also showed thunderstorm microbursts in which surface winds exceeded the winds aloft. Robert Sinn of Thornton Tomasetti told ENR: “Other wind engineers would have scaled up [from boundary-layer wind data] without even thinking about it.” Peronto told Newsweek that the tower would “probably be the most comfortable tall building on the planet.”
Elevators and Vertical Transportation
KONE’s project reference – the controlling source for these figures, where press counts vary – lists 57 passenger elevators (29 MiniSpace and 21 MonoSpace single-deck units plus 7 double-deck), two JumpLift construction elevators that climb with the building, and eight escalators. Four lifts run KONE’s carbon-fiber UltraRope, which exists because steel rope becomes its own limiting weight at this travel height; the observation-deck journey exceeds 630 vertical meters at speeds around 10 meters per second. According to KONE’s reference, those four are MiniSpace units, and UltraRope helps cut their energy consumption by up to 15 percent on the run of more than 630 meters. The Register put numbers to the weight problem in 2013, relaying KONE’s own figures: at 500 meters of travel with a car for two dozen people, the total mass in motion of a steel-rope-hoisted system would be about 29,000 kilograms, against about 12,800 kilograms with UltraRope. KONE describes the rope as enabling travel of up to 1,000 meters. The tower will not have the world’s fastest elevators. Guangzhou CTF holds that record at roughly double the speed; its genuine superlatives are travel height and, at 630 meters, the world’s highest observation deck.
Mounib Hammoud of Jeddah Economic Company is quoted on KONE’s undated “Vertical Limit” page describing what the developer required: “KONE is the only vertical transportation service provider in the world capable of delivering what we need at the Jeddah Tower – specifically the capability of travelling at a speed of over 10 meters per second with Double Deck elevators to reach the highest liveable floor in the world in 52 seconds.” Sascha Brozek, who heads KONE’s major projects unit, on the same page: “Without a doubt, this is a project that pushes the industry’s limits to new heights and we are very proud to be an integral part of that journey.”
Height creates the same kind of problem for the building’s services. In his 2011 Arabian Business interview, Smith explained that water has to be pumped up in stages, using holding tanks at various levels, so that pressure does not build up in the pipes and burst them; the same report said the tower will have emergency refuge rooms every 20 floors. On fire, Smith said: “Any time you are fighting a fire in a tower, it’s localized to a particular floor or part of the building… You don’t have to completely evacuate the building…”
Façade and Envelope
Guardian Glass supplies the tower’s glazing, Building Enclosure Online reported in November 2017. The unit is a custom double-pane glass system: Guardian SunGuard Silver 20, a solar-reflective coating, on the exterior pane, and SunGuard Neutral 60, a low-E coating, on the interior pane. The glass is made at Guardian’s Al Jubail plant in Saudi Arabia. The same report put the total glass area at more than 400,000 square meters, roughly 55 football fields, and noted that the sky terrace’s glass floor is also Guardian’s. It gives no solar factor or U-value.
Installation lags well behind the structure. Kingdom Holding’s Q2 2026 results put the façade cladding at about a tenth complete, with more than 3,000 panels installed, when the structure stood at 430 meters. Upkeep will also be a large job: in its 2011 interview with Smith, Arabian Business reported that “it would take crews working around the clock for at least three months to clean the exterior because of the sheer size.”
Sky Terrace, Cranes, and Concrete Pumping
AS+GG’s project page places a sky terrace roughly 30 meters (98 feet) in diameter at level 157; in July 2026, Arabian Business put the same upper observation level “around the 160th floor.” The two sources differ, and neither has been reconciled by the owner. The terrace began as a helipad. Smith described the disc to Arabian Business in 2011: “The observation deck will stick out from the building in an 80ft-wide disc that was originally designed as a helicopter-landing platform… The idea was abandoned after several pilots judged that landing there would be too risky.” Architizer also records the helipad origin. The 2011 dimension and the architect’s current figure differ, and the project page is the later source. A Jeddah Economic Company image caption carried by New Atlas in January 2025 puts visibility from the top at about 120 kilometers (74.5 miles). In July 2026, Peronto told Arabian Business about the climb toward the sky terrace: “We’re pushing very aggressively to get to that major milestone.”
Cranes Today described the tower’s crane plan in February 2016. A Wolff 355 B luffing crane, with a 40-meter jib and a 28-tonne capacity, stood in the core on a 48-meter tower, with a second to follow; each climbs internally in steps of 12 to 15.5 meters, up to approximately 580 meters. The plan at the time was to move one luffer to a platform at 538 meters, for a hook height of 734 meters, and then to reassemble it at 630 meters above sea level for an ultimate hook height of almost 800 meters. Twelve Wolff 7532 saddle-jib cranes served the podium and ground works.
Concrete reaches the working levels by pump. In January 2025, Prince Alwaleed said the concrete could be pumped to 800 meters and that the firms involved were working toward 1,000 meters, New Atlas reported. In December 2015, ConcretePumpers.com reported four Schwing SP 8800 stationary pumps on the structure, each of more than 600 horsepower and rated to 3,523 psi.
Program, Residences, and Jeddah Economic City
The program stacks a Four Seasons hotel, serviced apartments, luxury residences, offices, and the observation levels through the tapering plan, the narrowing floor plates matching the shrinking space needs of each use going up. The commercial clock has started – Kingdom Holding’s third-quarter 2025 results announced that residences will go on sale in 2026, the first consumer-facing milestone in the project’s history.
Around it, Jeddah Economic City is further along than the tower’s fame suggests: Saudi Exchange disclosures record phase-one infrastructure complete across 1.3 million square meters – electricity, water, sewage, flood drainage, high-speed internet – and 27 kilometers of roads and street lighting built, with land plots going to developers from 2026 after a period of memoranda. The tower anchors and advertises a far larger undertaking – the 5.3-million-square-meter district carries a reported cost of around $20 billion, and the tower’s long-term role depends as much on how that district fills as on the final height.
What Remains Before 2028
Everything above the latest announced milestone remains, and it includes the hardest work:
- the taper’s upper reaches, where floor plates shrink as the wind strengthens
- the push to the observation zone, which Peronto’s dated estimate places in 2027
- the closure of the envelope
- the long conversion of a concrete frame into a commissioned, occupied building
The envelope shows the distance most clearly: at Kingdom Holding’s August 2026 filing, roughly a tenth of the façade cladding was in place against two thirds of the concrete. The 42-month contract program points to 2028, and in late September 2026 Jeddah Economic Company’s chief executive, Fabien Toscano, put the target at late 2028, later than the August 2028 month that earlier press reporting had carried. That target has a named contract behind it, but it is still a target, for a building with no completed precedent above one kilometer. In 2018, Jeddah Economic Company’s chief executive expected the tower to be “open for business by 2020.” Unlike that forecast and every earlier announcement of revival, this phase has a record: a continuous run of dated milestones since January 2025, disclosed through an exchange, an engineering firm’s updates, the owner’s statements, and now the contractor’s own. For the first time in a decade, the world’s tallest building is primarily a construction story.
How tall will Jeddah Tower be?
At least 1,000 meters (3,281 feet) – the exact final height is being withheld until completion, as it was with the Burj Khalifa. At 1,000 meters, it would stand 172 meters above the Burj Khalifa’s 828 meters; every taller figure in circulation is unconfirmed.
Is Jeddah Tower still being built?
Yes – it is actively being built. After a seven-year halt at 63 floors, construction resumed in January 2025 under a SAR 7.2 billion completion contract. In early September 2026 the structure passed Malaysia’s 452-meter Petronas Towers, as announced by Saudi Binladin Group’s senior executive project director and reported by Newsweek; the current figure is given in the Construction Status section. The owner reports a five-day floor cycle.
Who designed Jeddah Tower?
Adrian Smith + Gordon Gill Architecture designed the tower, with Adrian Smith, who led the Burj Khalifa’s design while at Skidmore, Owings & Merrill, and Gordon Gill as lead architects. The structural engineering is Thornton Tomasetti’s, extending the buttressed-core lineage that Bill Baker engineered at SOM for the Burj.
When will Jeddah Tower be completed?
The target is late 2028, as Jeddah Economic Company’s chief executive, Fabien Toscano, put it in late September 2026, resting on the contractor’s 42-month program signed in October 2024. Earlier press reporting had carried August 2028. It remains a target for a building without precedent at this height. At Kingdom Holding’s August 2026 filing, about two thirds of the concrete had been poured and about a tenth of the façade cladding was complete.
How many floors will Jeddah Tower have?
At least 157, per Adrian Smith + Gordon Gill Architecture – the figure the architects and the 2024 completion contract reporting agree on. An older count of 167 floors still circulates from earlier project documents; the current architect’s statement supersedes it.
How much does Jeddah Tower cost?
The firmest cost figure is the completion contract signed in October 2024, SAR 7.2 billion (about US$1.9 billion), including roughly SAR 1.1 billion attributed to prior works. Full-project cost estimates in press coverage range from $1.2 to $2.7 billion for the tower, within a Jeddah Economic City development reported around $20 billion – figures worth treating as estimates, since no consolidated total has been officially disclosed.
What will Jeddah Tower be used for?
Jeddah Tower will be used for a Four Seasons hotel, serviced apartments, luxury residences, offices, and the world’s highest observation deck at 630 meters, arranged vertically through the tapering plan as the anchor of the 5.3-million-square-meter Jeddah Economic City.
Who owns Jeddah Tower?
Jeddah Economic Company, the developer formed for the tower and its surrounding city, Kingdom Holding Company, chaired by Prince Alwaleed bin Talal, is the principal investor, with Saudi Binladin Group as contractor and an early shareholder. Officially, the project now carries the developer’s name: the Jeddah Economic Company Tower.
Is there a Jeddah Tower live camera?
No official live feed currently operates; the developer’s earlier construction cam went offline during the 2018 halt. Progress is documented instead through Thornton Tomasetti’s updates, AS+GG’s photo releases, and Kingdom Holding’s disclosures.
Resources
- Kingdom Holding Company – 2025 Financial Statement (March 25, 2026) and October 2, 2024, Saudi Exchange disclosure
- Kingdom Holding Company – Q2 2026 results (August 7, 2026), via Reuters/Zawya
- Kingdom Holding Company – Restart ceremony post, official X account (January 20, 2025)
- Kingdom Holding Company – Final licence release naming the competition field (February 21, 2012)
- Saudi Binladin Group / Ian Norman Miller – 454-meter announcement (September 2, 2026), via Newsweek (September 3, 2026) and Fast Company Middle East
- Thornton Tomasetti – Construction updates, January 6 and April 20, 2026
- Prince Alwaleed bin Talal – July 2026 site-visit announcement
- KONE – Jeddah Tower project reference (vertical transportation specifications) and “Vertical Limit” story page
- Adrian Smith + Gordon Gill Architecture – Project statements and April 2026 construction photography (via Dezeen, April 23, 2026); Jeddah Tower project page
- Newsweek – 100-floor report and John Peronto interview (April–June 2026)
- Gulf Business – Completion-contract report (October 2024)
- Zawya / MEP Middle East – Kingdom Holding statement coverage (March 2026)
- AGBI – Kingdom Holding Q3 2025 results coverage (November 2025)
- Adrian Smith + Gordon Gill Architecture – Republished Arabian Business interview with Adrian Smith (August 30, 2011) and Structure magazine article by Jon Galsworthy, RWDI (June 2016)
- Newsweek – 454-meter report (September 3, 2026)
- Arabian Business – Jeddah Tower after the anti-corruption campaign (February 8, 2018); John Peronto interview (July 3, 2026); Bill Baker interview (July 17, 2026); Level 118 report (October 6, 2026)
- MEED – Fabien Toscano at the Shaping Mega Projects conference (October 6, 2026)
- Construction Week Saudi (October 5, 2026) and Gulf News (October 6, 2026) – 116th-floor and late-2028 reports
- Mubasher – Kingdom Holding H1 2026 results from the Saudi Exchange filing (August 6, 2026); AGBI – results coverage (August 2026)
- The Media Line – JEC Tower progress report (August 5, 2026)
- France24 / AFP – Release of Bakr bin Laden (May 13, 2021)
- Dezeen – Construction restart (January 29, 2025)
- Designboom – Kingdom Tower design presentation (August 3, 2011)
- The Skyscraper Museum – Jeddah Tower, Supertall! entry
- Wikipedia – Jeddah Tower (project history, citing MEED)
- ENR – Foundation report (November 11, 2015); RWDI wind-engineering report (May 11, 2016)
- PR Newswire / Langan International – Foundation design announcement (August 16, 2011)
- Building Enclosure Online – Guardian Glass report (November 6, 2017)
- Cranes Today – Wolff crane report (February 15, 2016)
- ConcretePumpers.com – Schwing pumping report (December 30, 2015)
- The Register – KONE UltraRope report (June 18, 2013)
- Architizer – 10 Facts About Jeddah Tower (sky terrace origin)
- CTBUH Skyscraper Center – Jeddah Tower building data (parking, cladding suppliers)
- Gulf News – Height comparison coverage (January 2025)
- New Atlas – JEC Tower update series (January–October 2026)