The AI boom is giving old industrial sites a new appeal and sending other developments into farmland. The buildings that follow have demands—and possibilities—that extend well beyond their walls.
At Wilton International, an industrial estate near Middlesbrough in northeast England, developers have found new value in the existing industrial infrastructure. The site has a 240-megawatt connection to the electricity grid and generating plants of its own. For a company trying to build and operate a data center, those assets offer a head start on getting the power turned on, ahead of sites elsewhere still awaiting new electrical infrastructure.
Peter Ireton, Sembcorp UK’s business development director, explained the attraction to Reuters: “Wilton is almost uniquely placed in that it already has a large grid connection and on-site power assets.”
In May 2026, Sembcorp Energy UK announced a planning application with Digital Reef for an initial data-center development of up to 280 megawatts, subject to planning approval. Artificial intelligence is among the intended uses. The proposal draws on an industrial inheritance, though the inheritance being valued is different from the one architects usually discuss. The mill converted into apartments keeps its brick walls and tall windows. Here, the electrical supply is helping make the case for an entirely new building.
Wilton is one expression of a shift taking place wherever the demand for computing meets the slower business of construction. Companies want their machines installed quickly. Utilities need time to extend networks. Architects must accommodate equipment that may change before the building opens, while communities consider what the finished development will ask of their land, water and electricity.
The architecture emerging from these negotiations deserves closer attention than its blank walls generally receive. A data center contains decisions about structure, climate and maintenance as exacting as those in a hospital or laboratory. Outside, its equipment determines what neighbors see and hear. Its location may even determine whether the heat from its servers is discarded or used to warm a swimming pool.
Featured image: Telehouse North Two, viewed from the River Lea. Photo: Robert Lamb, via Wikimedia Commons, CC BY-SA 2.0; resized.
The value of a connection
The property industry’s term for Wilton’s advantage is “powered land.” It sounds reassuringly complete. In practice, a developer needs to distinguish an existing supply from a conditional connection offer, and both from an application somewhere in a queue. The ground may be ready to build on long before the network is ready to serve it.
Britain’s queue has grown extraordinarily quickly. Ofgem’s July 2026 consultation reported that contracted demand awaiting connection rose from 41 gigawatts in November 2024 to 125 gigawatts in June 2025. Data centers accounted for about 73 gigawatts. Great Britain’s peak electricity demand, the regulator noted, was approximately 45 gigawatts.
That does not mean a fleet of data centers is about to consume more electricity than the country uses at its busiest moment. The queue contains projects at different stages, some of which will shrink, slip or disappear. Ofgem’s concern is that relatively inexpensive reservations allow speculative developments to obstruct more credible ones. Its proposed reforms would attach stronger financial commitments and progress requirements to a place in line.
Meanwhile, developers are looking farther afield. JLL data reported by Reuters puts European projects scheduled for 2026–2028 an average of 175 kilometers (109 miles) from major data-center hubs. Projects delivered in 2022–2025 averaged 46 kilometers (29 miles). The later group is still a pipeline, but it gives a measure of the distances companies are prepared to consider.
The International Energy Agency expects electricity consumption by data centers worldwide to rise from about 485 terawatt-hours in 2025 to 950 terawatt-hours in 2030. That forecast covers the sector, including conventional computing, rather than AI alone. Berkeley Lab’s U.S. study places data centers at 11.8 percent of national electricity consumption in its 2030 reference case, within a range of 9.5 to 15.3 percent under different assumptions.
| Measure | What it describes | What it does not establish |
|---|---|---|
| kW, MW or GW | Power at a moment, or a stated equipment/connection capacity. | Annual energy consumption or how much capacity is actually in use. |
| kWh, MWh or TWh | Energy consumed over a stated period. | The peak power needed at any single moment. |
| PUE | Total facility energy divided by IT equipment energy, using the same boundary and period. | Embodied carbon, computing output, or total energy savings. |
Forecasts leave plenty of room for disagreement about how much computing will be needed. The infrastructure decisions cannot all wait for that disagreement to be settled. Land must be secured, equipment ordered and network work planned years ahead. A connection date begins to influence which parts of a campus get designed first.
At Fouju, in Seine-et-Marne, France, that timetable is unusually explicit. An agreement between transmission operator RTE and Campus IA anticipates an initial 240 megawatts by the end of 2027, rising to 700 megawatts before the end of 2029. The infrastructure is intended to permit eventual expansion to 1.4 gigawatts.
A campus planned around that agreement has several lives to accommodate. Its first buildings need working access, cooling and electrical services while much of the site remains unfinished. Later construction needs routes of its own, without cutting through the operations already underway. Equipment installed for the first phase must not occupy the only sensible location for the next.
These are familiar problems in hospital and university master plans. The difference is the pace of demand and the quantity of power attached to each stage. An electrical commitment gives the architect a timetable to draw around, but it leaves the difficult work of making each intermediate state function.
A room that keeps changing
Joy Hughes, who works with data-center clients at Gensler, describes a brief that often arrives with little freedom over the date. “When our clients come to us, they already have service agreements with end users set up with promised dates,” she said in an interview published by the practice.
Her colleague Ryan Cook described the change inside the building. Conventional cabinets in colocation facilities—where customers rent space and supporting services for their equipment—might draw four kilowatts, or eight or twelve. AI cabinets now exceed 100 kilowatts. Replacing the tenant’s equipment can require a substantial change to the landlord’s building.
NVIDIA’s DGX GB200 concentrates 72 graphics processors and 36 CPUs in a rack requiring roughly 120 kilowatts. Cold plates carry liquid past the processors to collect their heat, while other components still rely on fans. The rack brings two cooling requirements into the room together, along with considerably more electrical demand.
The liquid has to reach the equipment under controlled conditions. In one common arrangement, a coolant distribution unit transfers heat between a circuit serving the computers and a separate circuit connected to the building’s cooling plant. Keeping the fluids apart lets engineers control their quality, pressure and temperature independently. The pumps, filters, valves and heat exchanger need space close to the load, where technicians have access to them.

The effect on a drawing is cumulative. Pipes share the service zone with electrical distribution and communications cables. Racks need working space behind them. The floor must carry the installed equipment and support it along the route from the loading area. A cabinet that fits neatly in a row may still fail to make the turn through the corridor leading to it.
A section through the hall consequently explains things the floor plan cannot. It shows how much room remains above the racks, how a technician reaches a valve and how a replacement component passes through the building after every adjoining system has been installed. Space left empty for that purpose may look wasteful until the first large item needs replacing.
ASHRAE, the engineering society, identifies increased rack weight, service requirements and leak management among the design consequences of AI. Its guidance warns that developments in computing and cooling are moving faster than conventional building-design cycles. A hall designed around one generation of equipment may receive another by the time it opens.
Electrical distribution is changing under the same pressure. NVIDIA is developing an 800-volt direct-current architecture for future high-density facilities. Raising voltage reduces the current required to supply a given amount of power, which reduces the bulk of the conductors. The company’s technical account describes a practical limit to the existing approach: adding more conventional power equipment would take up rack space intended for computers.
Beyond the racks, transformers, switchgear, batteries and uninterruptible power supplies occupy their own rooms and routes. Resilience requires attention to their arrangement, not simply the purchase of spare equipment. Two electrical supplies sharing a vulnerable space may be exposed to the same failure. Maintenance routes need to remain usable while other systems stay live.
The pressure on space does not produce one inevitable building form. Telehouse North Two, whose first phase opened in London in 2016, rises through 11 storeys at the company’s Docklands campus. The location provides access to established network connections, including the London Internet Exchange. The building had good reasons to stay in the city.
Excool, its cooling supplier, documents how the section works. Units supply cooled air from one side of the halls; hot air returns through a ceiling void. Outdoor air reaches the cooling equipment through open-mesh gantries and is discharged through the facade, with the paths arranged to prevent recirculation.
That is an architectural response to a particular location. The circulation of air is organized vertically, allowing the building to occupy a constrained site rather than spread its supporting plant across open land. North Two predates today’s AI rack densities, and adapting it to new equipment would require its own assessment. Its existence nevertheless complicates the idea that data centers belong wherever land and electricity are cheapest. Staying close to other networks has produced an entirely different section.
Before the permanent equipment arrives
In Abilene, Texas, the power infrastructure for Lancium’s AI campus had to begin working before all its permanent equipment was available.
Mortenson, the engineering, procurement and construction contractor for power delivery, describes the sequence in its project account. Construction of a one-gigawatt, 345-kilovolt substation began in the second quarter of 2025. Its first transformer was energized that December. Three of the five main transformers were temporary units, installed while the permanent replacements moved through procurement.
A transfer bus and an in-service spare helped the team plan later changeovers with fewer interruptions. The substation reached its full energized configuration on March 10, 2026, with the last permanent replacements scheduled through October. Energization describes the available electrical infrastructure, rather than a gigawatt of computers already consuming power.
The installation occupies roughly five hectares (12.5 acres). Even before considering a server hall, the project has a substantial footprint devoted to delivering electricity. It has to accommodate the operation and replacement of equipment measured on a utility scale.
A general contractor coordinating the buildings works downstream of those commitments. The electrical room depends on the equipment expected to fill it; the equipment depends on what suppliers can deliver. A substitute with an acceptable rating may need a different footprint, maintenance clearance or access opening. That seemingly administrative purchasing decision then moves a wall.
Fast-track procurement is not new to construction. The difficulty here is the number of large, interdependent systems whose delivery dates affect one another. Hughes’s account of promised customer dates and Mortenson’s account of temporary transformers describe opposite ends of the same schedule.
The building must eventually demonstrate that its systems work together. Commissioning tests the interfaces as well as the individual components: what happens when a power source fails, when a cooling component is isolated, when controls have to transfer an operating load. The general contractor, engineers, suppliers and operations team need an agreed sequence for turning a construction site into a live facility.
Repetition offers a way to move some of that work into more predictable conditions. At Eagle Mountain in Utah, a Mortenson campus comprising 28 data halls and nearly 300 megawatts, the company began producing precast electrical ductbanks. A manufacturing facility in West Jordan went on to produce wall systems and hot-aisle containment.
A ductbank protects the conduits carrying electrical services below ground. Building sections in a factory takes part of the conduit placement, reinforcement and concrete work out of the trench. It replaces a sequence of field operations with a delivery and a lift, followed by the work of connecting the sections accurately.
Much of the remaining site work is concentrated at the connection between factory-made pieces. Its tolerances must accommodate the difference between controlled manufacturing and the ground on site. Module dimensions must suit transport and lifting. Enough staging space must survive in a site plan already crowded with plant and construction activity. A repeatable detail is valuable because the next crew does not have to resolve it again.
The demand for those crews remains uneven. In the AGC and NCCER’s 2026 survey, 58 percent of respondents who had worked on data centers reported greater competition for skilled workers; 49 percent reported wage pressure. These are reports from contractors, rather than proof that every surrounding building project has lost labor to AI. They identify a specific pressure on firms seeking the same electrical and mechanical expertise at the same time.
That gives a well-coordinated building a practical advantage. Clear connections and workable sequences leave fewer problems for scarce specialists to solve in the field. Prefabrication still depends on skilled installation and testing, but the general contractor has a better chance of receiving compatible systems rather than a collection of packages that first meet on site.
The decision underfoot
The pressure to deliver quickly might seem to leave little room for changing an established design. Two Microsoft data centers in Northern Virginia offer a more interesting response.
Gensler and structural engineer Thornton Tomasetti changed the floor assembly. Concrete foundations and steel frames remain, but cross-laminated timber panels replace the conventional slab-on-metal-deck arrangement. The panels are made from layers of timber bonded with their grain running in alternating directions. A thin concrete topping addresses durability and waterproofing requirements described in Microsoft’s account.
The timber works with the other materials rather than replacing them throughout the building. Its lower weight reduces demands on the supporting steel. Microsoft estimates that the hybrid approach cuts embodied carbon by 35 percent compared with conventional steel construction and 65 percent compared with a typical precast-concrete approach.
Those are the client’s estimates against two different construction baselines, not independently verified reductions in the environmental footprint of the whole computing operation. They are still substantial enough to make the floor assembly worth examining. Material decisions that disappear beneath equipment remain consequential after the opening photographs have been taken.
Thornton Tomasetti paired the structural change with a different approach to delivery. The engineers completed a coordinated digital model, including connection designs, before the steel detailer entered the process. According to the firm, bringing that work forward helped shorten the steel-delivery timetable. The design effort was concentrated earlier, where it could influence the material that reached the site.
The project is more useful as an architectural example than a generic claim that timber makes a building sustainable. It identifies the element replaced, the materials retained and a change in the way the structure was procured. It gives another team something to assess against its own loads, code requirements, supply chain and programme.
Gensler’s published designs extend the use of timber into employee spaces and the exterior. Those decisions concern people who spend their working lives in the facility; the structural panels perform a different job. A timber finish cannot stand in for a lower-carbon frame, though both may belong in the same building.
The distinction becomes important in a sector whose environmental claims often concern only electricity. Power Usage Effectiveness, or PUE, divides total facility energy by the energy used by the computing equipment. It is a useful measure of the supporting systems’ energy demand. It says nothing about the concrete under the plant or the steel above the hall, and an expanding facility may consume more electricity even as its ratio improves.
The Microsoft floor addresses a part of that account which operating efficiency leaves out. The savings should be judged on their stated terms. They neither excuse further demand for power nor become irrelevant because that demand exists. A profession accustomed to evaluating structure and material has a contribution to make here that is quite separate from dressing a technical building in a more agreeable facade.
The neighbors have a different brief
For someone living nearby, the pressing question may be whether the equipment is audible from home.
Loudoun County, Virginia, records more than 4,000 permitted backup generators serving over 200 data-center facilities. A typical unit produces about two megawatts. These engines generally spend their time waiting, with periodic tests; the county describes a typical exercise period of an hour a week. Cooling equipment creates a more persistent presence.
The county’s guidance distinguishes tonal sound—a concentrated hum or buzz—from broader background noise. Terrain, weather, time of day and the listener’s position affect what is heard. The relationship between a mechanical yard and a neighboring house needs closer examination than a buffer drawn as a green strip around a site.
Here, the section is as important as the landscape plan. A barrier must interrupt the relevant sound paths while allowing the plant to draw in and discharge air. Its effectiveness depends on the relative height of the equipment and the property it is meant to protect. Maintenance access, security and planting need room along the same boundary.
A row of trees can screen a view; that does not make it an acoustic enclosure. Similarly, a composed elevation on the main road says little about a generator yard facing houses on another side. The public encounters all the equipment that the architectural image is tempted to leave out.
In Saline Township, Michigan, the disagreement began earlier, with the prospect of developing farmland. Tammie Bruneau, who organized opposition, told Reuters: “Most people aren’t interested in some massive development here.” She added: “They’re interested in protecting the farmland.”
The township rejected the requested rezoning. A lawsuit followed, and in October 2025 WEMU reported that trustees had approved a proposed consent agreement and sent it to the owners and developer for acceptance. It included a requirement for the company to repair neighboring wells if its operations caused them to run dry. At the time of that report, the developer still had to agree to the proposal.
Township attorney Fred Lucas warned against interpreting the decision as a statement of what residents preferred. “People have to understand this was not a choice between do we want it or not,” he told the station. The consequences of continuing the legal dispute had become part of the choice.
A condition about wells does something a rendering cannot: it identifies a possible harm, the people exposed and a responsibility to act. The adequacy of that remedy is a separate question from the development’s landscaping. The agreement makes visible the obligations that travel with a building into its surroundings.
Architecture has limits in such a dispute. A quieter mechanical yard will not settle an objection to the loss of farmland. Better drainage will not decide who should bear the cost of a wider electricity network. Yet those limits are no reason to postpone decisions about the yard or the drainage until permission has been secured.
Architects and general contractors have useful work to do before a proposal hardens. Equipment placement, service routes, setbacks and sound mitigation affect neighbors long after construction ends. They are easier to negotiate while the site still admits alternatives than when a completed engineering layout is presented as the only workable arrangement.
Where the heat belongs
The competition for land and power has a different expression in Singapore, where the government allocates additional data-center capacity through a controlled application process. Its second call, launched in December 2025, offered at least 200 megawatts, tied to sustainability and strategic criteria. EDB and IMDA have since provisionally allocated 200 megawatts to four operators through that exercise; allocation is distinct from operational capacity.
CBRE’s 2026 assessment describes opportunities to upgrade existing facilities alongside a constrained supply of new space. It identifies neighboring Johor, Malaysia, among the markets attracting larger developments through available land and power. Companies seeking expansion across the border retain an interest in Singapore’s established customers and connections.
For architects working on existing facilities, expansion is a problem of occupied space. A new cooling pipe has to find a route through a service zone already carrying cables and other systems. Plant must enter through existing openings. Structural strengthening may consume clearance below a floor. Customers’ equipment may need to keep running while the work proceeds around it.
The final layout tells only part of that story. Temporary routes, isolation zones and the order in which installations come into service determine whether the proposed changes are workable. The ability to make a convincing drawing of the finished hall is less useful if there is no acceptable way to get there.
The climate remains part of the calculation on either side of the border. Malaysian officials told Reuters that data centers’ share of electricity consumption reached 9.3 percent in the second week of August 2026, against a year-to-date average of about 7 percent. They attributed part of the increase to cooling demand during higher temperatures.
Liquid cooling at the processor does not dispose of the heat. It carries it to another system, which must transfer it outside or deliver it to somebody who can use it. Dry coolers reject heat to outdoor air; evaporative equipment uses water to assist the process. The choice influences electricity demand, water consumption and the amount of equipment around the building.
Higher operating temperatures offer some room for improvement. ASHRAE describes systems supporting facility-water supply at 45 ℃ (113 ℉), with returns reaching 65 ℃ (149 ℉). For equipment designed to accept those conditions, the larger temperature difference between the water and the air permits dry cooling in more circumstances. The useful temperature depends on the hardware being cooled.
Water accounting requires similar attention to the system actually being built. Researchers Ana Pinheiro Privette, Ana Barros and Ximing Cai distinguish direct facility consumption from water used in electricity generation and hardware manufacture. A closed loop beside the servers does not tell a planning authority how much water the cooling plant will need during a hot summer. The source of that water and the condition of the local watershed matter more to a neighbor than a global average.
Pampa Energía’s proposed development in Patagonia illustrates a different limit on favorable environmental conditions. The company is studying a data center of up to 500 megawatts beside its Loma de la Lata power plant in Neuquén. Connectivity and financing remain obstacles. Hadassa Lutz, co-founder of Cloud2Ground, told Reuters: “But saying you have power is not enough.” Electricity gives the proposal a reason to exist; other infrastructure and commercial commitments must still come together.
Saint-Denis, north of Paris, offers a reason for a data center to remain close to a city that has little to do with delivering information. Equinix’s PA10 facility supplies heat to a district network serving the Plaine Saulnier development and the Olympic Aquatic Centre. According to the local heat authority, SMIREC, the recovery system began operating on June 10, 2024.

Water available from the data center is approximately 28 ℃ (82 ℉). Heat pumps raise the temperature for the network. Separate systems exchange energy without sending cooling water from the computer building into the swimming pool. The aquatic center receives heat through infrastructure intended to serve a wider district.

Equinix committed to providing the recovered heat free for 15 years. Free heat did not mean a free heating system. Pumps, exchangers and pipework required investment, and somebody had to operate them. SMIREC records years of discussions and an agreement formalized in 2022, with public support helping the connection reach construction.
The arrangement gives proximity a value missing from a map of electrical capacity. A distant campus may have power to spare but no nearby customer for its heat. In a city, an apartment district, hospital or swimming pool may need warmth—provided the temperatures, distance and timing suit the exchange. Arup’s work on recovery schemes emphasizes bringing the producer and potential users together during feasibility and concept design, while routes and space for equipment remain open to discussion.
Heat recovery will not make every proposed data center a good neighbor. The connection at Saint-Denis is useful precisely because it depends on local circumstances rather than a general promise attached to server heat. A pool needed energy, a nearby facility had heat to shed, and a district operator had a means of joining them.
The Olympic Aquatic Centre was the system’s first beneficiary. By June 2024, after the agreements, heat pumps and connecting infrastructure were in place, the same computing equipment that required cooling could supply part of a public building’s warmth. The two buildings had become useful to each other in a way neither could achieve within its own property line.
Resources
- Sembcorp Energy UK – “Sembcorp Energy UK Announces Phase 1 of Wilton International Data Centre” (2026).
- Reuters – “Powered Land and Zombie Projects: Real Estate in the Age of AI” (Kate Holton and Lucy Raitano, 2026).
- Ofgem – “Curate – Demand Connections Reform” (2026).
- Reuters – “Europe AI Data Centres Seek Cheaper, Quicker Energy and Land” (Simon Jessop and Iain Withers, 2026).
- International Energy Agency – “Key Questions on Energy and AI” (2026).
- Lawrence Berkeley National Laboratory – “United States Data Center Energy Usage Report: 2025 Update” (Sarah Josephine Smith and co-authors, 2026).
- RTE – “Campus IA et RTE Signent un Contrat de Raccordement Accéléré pour un Campus d’Infrastructures Numériques en Région Parisienne” (2026).
- Gensler – “How the AI Gold Rush Is Influencing Data Center Design Trends” (Joy Hughes and Ryan Cook, 2025).
- NVIDIA – “DGX GB Rack Scale Systems User Guide: Hardware” (2026).
- Vertiv – “Understanding Coolant Distribution Units (CDUs) for Liquid Cooling” (accessed September 2026).
- ASHRAE – “AI Data Center Energy Performance Framework: Integrated Design Principles” (2026).
- NVIDIA – “NVIDIA 800 VDC Architecture Will Power the Next Generation of AI Factories” (2025).
- Telehouse – “Telehouse Completes First Phase of Its London Docklands North Two Data Center with LINX On-board” (2016).
- Excool – “Excool Project Insight – Telehouse, Docklands, London” (2021).
- Mortenson – “Abilene AI Data Center & Power Delivery” (project account, accessed September 2026).
- Mortenson – “Eagle Mountain Data Center Construction” (project account, accessed September 2026).
- Associated General Contractors of America / NCCER – “Construction Workforce Shortages Remain Acute Despite ‘Soft’ Market Conditions as Data Centers Strain Labor Supply, Survey Finds” (2026).
- Microsoft – “Microsoft Builds First Datacenters with Wood to Slash Carbon Emissions” (Sally Beatty, 2024).
- Thornton Tomasetti – “Microsoft Mass Timber Data Centers” (project account, accessed September 2026).
- Gensler – “Microsoft Mass Timber Hyperscale Data Centers” (project account, accessed September 2026).
- ASHRAE – “AI Data Center Energy Performance Framework: Energy and Thermal Efficiency” (2026).
- Loudoun County – “Data Centers: Energy Issues & Considerations” and “Noise & Air Quality Concerns” (accessed September 2026).
- Reuters – “Americans Are Angry About Data Centers. Politicians Are Feeling the Pressure” (Helen Coster and Valerie Volcovici, 2026).
- WEMU – “Saline Township Approves Consent Agreement for Rejected Data Center” (Kevin Meerschaert, 2025).
- Singapore Economic Development Board / IMDA – “Launch of Second Data Centre – Call for Application” (2025); “Four Data Centre Proposals Selected as Part of Second Data Centre – Call for Application” (2026).
- CBRE – “Global Data Center Trends 2026” (2026).
- Reuters – “Malaysia’s Data Centres Guzzling More Power as Temperatures Soar, Officials Say” (Ashley Tang, 2026).
- AGU Advances – “Data Centers Water Footprint: The Need for More Transparency” (Ana Pinheiro Privette, Ana Barros and Ximing Cai, 2026).
- Reuters – “Tech Explores Argentina’s Patagonia for Mega Data Centers” (Leila Miller, 2026).
- SMIREC – “Inauguration de la Récupération de la Chaleur Fatale du Data Center à Saint-Denis le 21 Juin 2024” (2024).
- ENGIE Solutions – “La ZAC Plaine Saulnier et le Centre Aquatique Olympique de Saint-Denis Seront Alimentés à 75 % par des Énergies Renouvelables” (2024).
- Arup – “Data Centres, Heat Reuse and the Future of Circular Energy Systems” (John Bynum, 2026).